1 00:00:00,05 --> 00:00:03,08 - [Instructor] Okay, so let's make those EVM equations. 2 00:00:03,08 --> 00:00:07,05 Over here, under I, I'm going to type in SPI 3 00:00:07,05 --> 00:00:09,04 for scheduled performance index. 4 00:00:09,04 --> 00:00:14,09 Then in column J, I'll do CPI for cost performance index. 5 00:00:14,09 --> 00:00:25,00 And then in K, I am going to write safety incident count. 6 00:00:25,00 --> 00:00:28,09 So for the SPI, recall that that's going to be the earned value 7 00:00:28,09 --> 00:00:31,05 divided by the planned value. 8 00:00:31,05 --> 00:00:37,05 And the cost performance is going to be the earned value 9 00:00:37,05 --> 00:00:39,08 divided by the actual cost. 10 00:00:39,08 --> 00:00:42,05 And it's always a good idea when you do these divisions 11 00:00:42,05 --> 00:00:45,00 just to put an if error around it. 12 00:00:45,00 --> 00:00:46,05 So we're going to make that zero here, 13 00:00:46,05 --> 00:00:50,00 and then same deal over here. 14 00:00:50,00 --> 00:00:52,08 And then, finally, we want to do the safety incident count. 15 00:00:52,08 --> 00:00:57,03 So in this case, we're going to do a count if, 16 00:00:57,03 --> 00:01:02,03 and the range is going to be over on safety incidents. 17 00:01:02,03 --> 00:01:07,04 We're just going to do the entire project list here. 18 00:01:07,04 --> 00:01:08,06 I'll hit comma right over here, 19 00:01:08,06 --> 00:01:11,06 and then we'll go back to project data 20 00:01:11,06 --> 00:01:13,01 and select the project name over here. 21 00:01:13,01 --> 00:01:15,01 So this is just going to link the two tables. 22 00:01:15,01 --> 00:01:16,07 If it finds that name there, 23 00:01:16,07 --> 00:01:19,05 that means that there is a safety violation. 24 00:01:19,05 --> 00:01:21,06 Okay, and so now we have our count. 25 00:01:21,06 --> 00:01:24,03 So now we have our metrics that we are going to use 26 00:01:24,03 --> 00:01:27,00 to create our dashboard.